Phase
3 - Multipurpose Instructional Building
Includes:
8 classrooms, small snack bar, Academic Student Success
Center, Department of Instruction Offices & Adjunct Faculty
Support
Center, and some landscaping/infrastructure
Aprox: 15,330 square feet
Budgeted at: $3,152,000
Scheduled to Open: Summer 2006, We will break ground Spring
2005 |
|
| |
Phase
4 - University Center & Trades/Physical Plant Facilities
Includes:
University Center - Library, Community/Dining Center, Bookstore,
Central
Administration Offices
Trades/ Physical Plant - Specialized Trades classrooms &
labs,
Facilities Management Offices & Workspaces
Landscaping & Infrastructure
aprox. 27,692 Total Square Feet |
|